Project duration: 1 December 2004 to May 2007

   

A kick-Off Meeting was held on 10 - 11 December 2003 in Sophia Antipolis

The 1st progress meeting on 9 - 10 February 2004 in Zurich

The 2nd progess meeting took place at DLR in Stuttgart on 15 - 16 September 2004 

The service review and the 3rd progress meeting was held on 17 November 2004 at ESA-ESRIN

The 4th progress meeting was held in Augsburg on 3 - 4 March 2005

A 5th progress meeting was held at the University of Oldenburg in October 2005.

The market review was sucessfully finalised in November 2005 at ESA-ESRIN 

A 6th progress meeting was organised on 24 - 25 April 2006 In Paris.

The 7th progress meeting was held on 3 - 4 December at Livorno, Italy.

The final presentation will be in June 2007 at ESA-ESRIN.